QTS Irving: DC 3 Development

Progress continues as we build out our campus in Irving, Texas, with the addition of Data Center 3.  We hope you've been following our journey on the Construction Blog, but if you haven't, please take a moment to view the updates we've posted to date.  

 

irv-dc3-november2018-page image-campus 2

 

On the heels of our first greenfield mega data center build in Ashburn, we're excited for this 427,000 sq ft addition to our Irving campus. With this 32MW expansion, our Irving campus now boasts 113MW of critical power, expandable to 156MW, courtesy of the QTS-owned on-site power substation.  When DC 3 comes on-line, our total campus sq ft will be an impressive total of 1,077,000.

 

irv-dc3-november2018-page image-angle

 

We look forward to sharing our progress with you as we build out this mega data center campus.  For more information about the ongoing development of this site and others, including upcoming availability, contact our Hyperscale Sales Team.

 

irv-dc3-november2018-page image-campus